goes Agile: Don't Repeat our Mistakes
summary
Qik joins Skype in 2011 and a promised March release fails because Skype forces work through ~50 release vehicles (RVs), creating chains of six RVs per product and blowing up cycle time (measured cycle efficiency ~30% vs. typical scrum ~20%). The team visualizes delivery with a product board, reduces 23 to 8 user stories as the priority, forms an integration team, fixes a May 2013 release date and restores regular, demonstrable releases.
AI-written summary · about
chapters (10)
- 0:00Start
- 4:28Advantages
- 9:06Release Vehicles (RV)
- 11:30RV reports
- 14:21Frontend
- 15:59RV diagram
- 20:05Working on a typical feature
- 24:23Little's Law
- 24:49Queueing theory
- 30:14Summary