Runs continuous delivery for an exchange handling $10 billion a day, keeping every commit a potential release candidate and using 7,000 end-to-end acceptance tests that run hourly. Releases every two weeks with identical binaries, scripts and deployments across environments; staging rehearsals run ~three times a day. Adds lightweight “testing in live” checks (initially five production tests) focused on component plumbing, isolates test traffic via virtual venues, and uses a rotating build-sheriff to keep intermittent failures down to two or three per run.
AI-written summary · about
chapters (6)
- 0:00Intro
- 3:25Functional Testing
- 5:46Releases
- 8:28Testing-in-Live
- 11:00Example Live Test Case