Negotiation and padding in software project estimates

links:none on file
slides:none on file

A study claims negotiation and padding routinely reshape software estimates. Researchers spend three months observing four teams and conduct followup interviews. Methods include planning-poker based estimates and session observation. Findings show padding often buys contingency but also routinely hides technical debt and unfinished work, driven by power dynamics and layer mismatches. Recommendation is to surface developers’ reasons and translate refactoring or maintenance into customer-facing value so estimates reflect true effort.

AI-written summary · about

  1. 0:00Introduction
  2. 0:27Stakeholders
  3. 1:34Factors affecting estimates
  4. 3:05Observation studies
  5. 4:10Agile practices
  6. 6:40Risk management
  7. 7:25Hiding tails
  8. 8:24Adding
  9. 9:05Conclusion
  10. 10:52Outro
~/search
type to search 6,249 conferences, 138,987 speakers and 185,172 talks
~/help
cmdctrl k
search every conference, speaker and series
/
focus the filter search
h
home
c
conferences
s
speakers
e
series
t
light / dark — the status bar button does the same
?
this help
esc
close this, then clear every filter — or just the search, while you are typing in it

Ignored while you are typing. Pages without a filter rail have no search to focus.