On June 29, 2025 125 routes changed overnight and roughly about 10% of stops were removed; WMATA publishes GTFS but restricts reuse so mappers must recreate routes in OSM. The project upgrades data to the PTV2 schema, uses JOSM for edits and the Relate a fine editor to rapidly build continuous relations, finishes the core network in about two months, publishes a project wiki for upkeep, and sparks adjacent mapping of Loudoun and Prince George’s systems.