Josh Raines, MIT | PI World 2018
summary
MIT uses the OSIsoft PI system to aggregate meters across a ~120 campus and finds concrete fixes: a stuck control valve lets chill water flow drop from 1,200 to 150 gpm, cutting plant load and saving $60,000–$80,000 per year. Meter rollout expands over three years, cogen capacity rises from ~25 MW toward 40 MW to shave grid peaks, and work is underway to ingest high‑speed PMU feeds for rapid fault localization and islanding decisions.
AI-written summary · about
chapters (11)
- 0:00Introduction and MIT overview
- 1:04Campus energy metering explained
- 2:08Building as a living entity
- 3:32Data-driven efficiency insights
- 4:15Simultaneous heating and cooling case
- 5:21Chill water delta temperature fix
- 6:46Peak consumption management
- 7:35Cogen system revitalization
- 7:56Future opportunities with PMU data
- 8:59Long-term building performance analysis
- 9:43Closing remarks