Wattum reports concrete build numbers: an early New Jersey site costs $800,000 per MW at ~$0.08/kWh, an adapted Niagara Falls build hits $200,000 per MW at ~4.2¢/kWh, and a 16 MW Kazakhstan farm reaches $120,000 per MW with ~3.4¢/kWh. Container deployments install in three–four months for about $100,000 per MW. Company inventory sits near $10M, sales exceed $100M with a $160M year target. Operate on reuse and standardized designs, pre-order from trusted stock, and plan for shipping, duties and quick payment.